Licence conditions for pollution studies and reduction program


  

Licence conditions for pollution studies and reduction programs

Summary
 
Licence number: 779
Title: PRP 16 - Stormwater Pipeline Program
Start date: 10 Feb 2017
 
Licence Condition
Stormwater Pipeline Report By 30 SEPTEMBER 2017, the licensee must provide a report to the EPA that investigates and determines the most feasible options to upgrade the stormwater management system.  The report must include, but need not be limited to the following: 1.        The replacement of relevant sections of the Stormwater Pipelines; 2.        The re-lining of relevant sections of the Stormwater Pipelines; and 3.        the decommissioning of any redundant elements of the Stormwater Pipelines  
Stormwater System Works By 30 MARCH 2021, the licensee must complete all Stormwater System Works identified as part of the Bayswater Power Station Stormwater Pipeline Report.